Action Items:
Approved the 2020 Management Discussion & Analysis (audit)
Approved the board meeting dates for November and December 2021
Approved an increase to new building project budget
Approved the Rio Community Library Technology Services Agreement
Present: B.
Clendenning, S. Elwell, N. Foth, M. Furgal, J. Healy-Plotkin, J. Honl, N. Long,
M. Nelson, R. Nelson, T. Peterson, G. Poulson, T. Walske
Absent: N. Brien, P. Cox
Excused: F. Cherney, K. Williams
Recorder: H. Moe
SCLS Staff Present: M. Van Pelt, K. Goeden
Call to Order: 12: 15 p.m. J. Healy-Plotkin, President
a. Introduction of guests/visitors: Devin Flanigan, Keller, Inc., David Odahl, Wegner CPAs
b. Changes/additions to the agenda: None
c.
Requests to address the Board: J. Healy- Plotkin noted Rob Nelson has been
elected Mayor of Baraboo. B. Clendenning inquired about the purpose of
“changes/additions to the agenda” and if any changes would be “legal”. M. Van
Pelt noted changes to the agenda could include an action item that needed to be
removed and added at another meeting. An action item cannot be added, but it
can be removed. M. Nelson noted it can also be used to rearrange the order of
the agenda to accommodate guests/speakers.
Approval of previous meeting minutes: 3/25/2021
a.
Motion: B. Clendenning moved approval. T. Walske seconded.
b. Changes or corrections: None
c.
Vote: Motion carried.
Bills for Payments: The payment amount is $125,211.20
a. Motion. G. Poulson moved approval of the bills for payment. N. Long seconded.
b. Discussion: A question was raised regarding the Skill Path and Darcy Louma invoice. Skill Path is a subscription for all SCLS staff who would like to participate in unlimited virtual seminars and webinars on many different topics. Darcy Louma is a company that was hired to present training to SCLS staff on helpfulness, which is one of the SCLS quality standards.
c. Vote: Motion carried.
Financial Statements: K.
Goeden provided an overview of the financial statements.
Presentation: Audit Report – David Odahl of Wegner CPAs provided an
overview of the 2020 Management Discussion & Analysis. A question was
raised whether he felt SCLS needed to continue the process of having a trustee
examine the bills for payment monthly. D. Odahl noted that if the board feels
they are receiving all the information needed, they do not need to review
them. SCLS has three people internally reviewing the bills for payment prior
to the financials being presented to the board so there are checks and balances
in place.
Committee Reports:
a. Advocacy – The joint finance committee has been traveling throughout the state and moving forward on the budget process. DPI and WLA are looking out for libraries. B. Clendenning attended the joint finance committee in Rhinelander and noted there was a speaker representing WLA. M. Van Pelt noted LD&L sent out a call to attend these meetings and all of the slots were filled.
b. Strategic Plan: S. Elwell, N. Long, N. Foth, J. Healy-Plotkin, M. Van Pelt. The first strategic plan meeting will be held May 19 at 10:00 am. J. Healy-Plotkin requested G. Poulson schedule a Bylaws Committee meeting since Marathon County has delayed its decision to join SCLS.
Action Items:
a. Approve 2020 Management Discussion & Analysis (audit)
i. Motion: M. Furgal moved approval of the 2020 Management Discussion & Analysis. N. Foth seconded.
ii.
Discussion: None
iii. Vote: Motion Carried
b. Approve board meeting dates for November and December 2021
Friday, November 19
Friday, December 17
i. Motion: M. Furgal moved approval to hold the SCLS board meetings on November 19th and December 17th. B. Clendenning seconded.
ii.
Discussion: None
iii. Vote: Motion Carried
c.
Approve increase
to new building project budget – Devin Flanigan, Keller Inc. noted the demand
for building materials is not meeting supply, which is increasing the cost of
materials. Manufacturers were quarantined for a large amount of time and inventories
depleted but demand is ramping up and supply costs are 5 to 10% higher
comparable to last year. The BNAW discussed the issue of increased costs of
supply and with the advice from Keller Inc., determined they needed to request
additional funds of $500,000 to accommodate the increases. The work group also
looked into whether the size of the building could be decreased, but in doing
so, the conference rooms, huddle rooms, and up to 20 offices would need to be
removed, which defeats the purpose of a building that can accommodate all
staff. In two years’ time, it has been determined that SCLS will be paying
approximately $33,000 in rent (due to increases by the landlords), which would
be the equivalent of a monthly mortgage payment with the additional $500,000
added to the building budget.
i. Motion: M. Furgal moved to increase the new building project budget
by $500,000.I ii. Clendenning seconded.
iii.
Discussion: G. Poulson inquired about contingency fund use. The goal is not to
dip into contingency and in two years’ time, the amount in contingency may be
higher. SCLS is borrowing $5.5 million from the Board of Commissioners of Public
Land at a 4% fixed interest rate for 20 years with no down payment. This
lending program is only available to public entities. M. Nelson inquired if
there was any consideration given to simply pausing further development for a
year to see if prices reduce and if so, what would be the ramification. K.
Goeden noted the BNAW did not consider that option since our lease ends in May
of 2023 and that is the target date to complete the project.
iv. Vote: Motion Carried
d. Approve Rio Community Library Technology Services Agreement
i. Motion: N. Long moved approval of the Rio Community Library Technology Services Agreement. M. Furgal seconded.
ii.
Discussion: None
iii. Vote: Motion Carried
SCLS Foundation Report:
M. Van Pelt noted $6,000 has been received for the Cornerstone event this
year.
System Director's Report:
You
may view the System Director report online. M. Van Pelt noted Rio will be
joining LINKcat in June. Marathon County has postposed making a decision to
join SCLS. M. Nelson inquired how this decision will affect the northern
delivery hub. PLSR is moving forward on their statewide delivery plan with the
southern hub to be completed first and the northern hub later. SCLS is interested
in having the northern delivery hub at Marathon County and we can pursue it independently
of PLSR.
Discussion:
a. Do we
want to resume the examination of bills by trustees?
The
following ideas were shared:
Continue to have a trustee review the bills in person. Should this start now
or when in person meetings can take place?
Is there a difference between reviewing the bills in person versus the information that is provided monthly to the board? Yes.
Could the board treasurer be the person responsible to review the bills for
payment monthly instead of rotating through the board members? This is a
possibility but if it were to occur, it would happen in 2022 so the elected
treasurer would be aware of the additional duties required of the position.
Would
it be possible to scan the documents and send an electronic version for the
trustees to review? It would be very time consuming and additional work.
It was decided to table the conversation until September.
Administrative
Council (AC) Report: 4/15/2021.
You may view the minutes online.
Other Business: None
Information
Sharing: F. Cherney
is not feeling well. SCLS will send a card on behalf of the board.
Adjournment: 1:47 p.m.