Building
Needs Assessment Work Group Agenda
July
7, 2022 10:00 a.m. – 12:00 p.m.
Hybrid
Meeting
Present:
Jean
Anderson SCLS Consulting
Services Coordinator
Corey
Baumann SCLS Delivery Services
Coordinator
Nan
Brien SCLS Board
Trustee
Kerrie
Goeden SCLS HR &
Finance Coordinator
Gary
Poulson SCLS Board Trustee
Jesse
Stewart SCLS Fleet Manager
Vicki
Teal SCLS Technology
Services Coordinator
Kristi
Williams SCLS Board Trustee
Martha
Van Pelt SCLS Director
Guests:
Susan Feith SCLS Board Trustee
Devin Flanigan Keller Inc. Project Manager
David Haug Lighthouse Realty
Deb
Haeffner SCLS Consultant
Rob
Lindstrom Keller Architect
Call to Order by K. Goeden 10:02
Approval of previous meeting minutes: June 16, 2022
a.
Motion by J. Stewart to approve the minutes
b.
Second by J. Anderson
c. Approved.
K. Williams and G. Poulson abstain
Reports: None
Discussion:
·
Walton Commons
o
Review estimated budget
§ D. Flanigan shared
budget documents for Walton Commons-Facility
Cost Analysis
§ Already spent $432,698
§ To complete new building at Walton Commons the
estimate is $7.6 million - $8.1 million
·
G. Poulson feels comfortable walking
away from Walton Commons
·
N. Brien feels like walking away since
the revised building is not what we want or need
·
C. Baumann is not optimistic about the
building coming in within budget
·
J. Anderson was excited about the
building, she is new to the group as of January 2022, but it is overpriced and
not the building we want
§ 100% consensus was reached to no
longer pursue Walton Commons. BNAW’s recommendation
to be put on the July 28, SCLS Board agenda.
After the board approval and vote, D. Haug
will contact the City of Madison to conduct the necessary next steps.
**
Walton Commons Option A was revisited at the end of the meeting. D. Flanigan to
follow up on this option. See notes
below.
·
Lakeland
University Property
o
Reviewed
proposed floor plans
Two options on Lakeland:
1.
Complete
interior remodel of Lakeland with a delivery addition of 12,000 sf
a.
This
version allows the sorting floor and delivery offices to be moved into the
Lakeland building and then a smaller addition for delivery would be required.
i.
Concerns
that this version removes most of the features of the current building that the
team likes (wide hallway, lobby, reception, kitchenette, etc)
and the additional cost of remodeling more of the office side in addition to
building delivery space.
ii.
Advantage
is that the space is utilized more efficiently and allows a portion of delivery
to be included in the existing building, which means a smaller addition.
iii.
Question
is which version costs less and provides what we want?
iv.
Concerns
with the delivery portion of the sketch.
It does not include a drive through or angled parking and has the docks
unloading into the garage instead of into the sort floor. First draft did not include wash bay.
2.
Keep
as much of the original Lakeland building as possible intact and remodel a
portion of it. This would require a
larger delivery addition of 15,000 sf.
a.
This
version essentially makes the Lakeland Building “HQ” and Delivery would be a
separate addition.
b.
Concerns
about this version include the cost of a larger addition, the possible need for
more land in order to accommodate the larger addition and the less efficient
use of existing space within the Lakeland building.
c.
The
main question remains: Which version
costs less and gives us what we need for both HQ and Delivery?
Consensus of group was that either
option will work at this time. We will continue to explore both of these
options. A lot of information is needed
in order to answer the viability questions.
Parking requirements, cost of additional land, covenants and building
requirements, easements, etc. Team will
work on gathering the necessary information.
Questions
that need answers before moving forward:
Cross
easements agreements for parking?
Snow removal, use of different lots
What
are the covenants in place attached to the parcel?
Which is the driveway to access
Lakeland University?
Ground
lease details?
Refer
to CSM for site parameters?
What
are the Dane County Airport building design rules? Probably stricter than Walton Commons requirements–
probably will require a building that matches the higher quality of exterior
materials on the main building – meaning the warehouse at Lakeland will cost
more than the same warehouse on Walton Commons.
D. Haug thinks we should check to see if we
can use cheaper materials on a percentage of the building that does not face
Packers Avenue? Since the existing building uses higher quality materials on
all sides, perhaps the addition will require lesser quality materials based on
a percentage of the total?
Is
there a required number of parking spaces per square foot and how is the number
calculated?
Lakeland area
architectural review committee? “Design and Review Committee” – what are their
requirements?
What sides constitute the
façade? (Does it includes both Pankratz & Packers
Ave?). This relates to how many sides require using expensive materials.
130 ft
needed for drive thru in delivery, too narrow on current map for Lakeland. Do
we have access to do this? Enough
land? Parking available?
How much to purchase extra
“dogleg” strip of land west of Lakeland?
K. Goeden
will send R. Lindstrom covenants and legal documents.
R. Lindstrom will sketch
up both plans. He will attempt to revise
the delivery addition to include a drive through and moving the docks to be
adjacent to the sorting floor. Needs
answers from covenants and easements.
Floor Plan and site layout. Need
to know how much land is needed.
D. Flanigan
will work on rough estimates for both options.
Engineers working on ball park figures.
D. Flanigan
will send sketches so work group can move “puzzle pieces” within Lakeland
building and provide feedback for 2 options for next meeting. The feedback will show how to layout the
rooms in the building with attention to placing rooms/services in proximity to
people involved with the service and access points to other related services.
D. Haug
needs to find cost of additional land and which is viable west or north side.
Need 5,000 or 10,000 ft additional toward Pankratz or pan handle/dog leg.
K. Goeden will contact
lawyer for information on the title work.
**After discussing the Walton
Commons and Lakeland options, K. Williams asked the group to consider Option A
(below). This plan would include
building the original Walton Commons plan ($9 million plan), SCLS would own $7
million of it, Keller would own the rest (roughly 25%)
and Keller would lease back their portion to SCLS. D. Flanigan was
asked to approach Keller about this option to ascertain whether or not they
will consider it. If yes, what lease terms would they need from SCLS in order
to proceed with this option?
D. Flanigan
will bring cost and terms of Keller leasing 25% of Walton
Commons building back to SCLS to the 7/21/22 BNAW meeting.
It was agreed to hold off on
any action (informing of building site changes to Pocan
and Baldwin) on the federal grants for solar until we have a definite site for
building.
Discuss BNAW schedule
– Set up weekly check- ins
on Friday for D. Haug, D. Flanigan,
M. Van Pelt and K. Goeden on Blue Jeans
Full List of Options to Consider: Review at next meeting, ran out of
time.
Option A: Full building as it is 32,000 sq. ft. Update next meeting.
·
Keller assist with ownership of building; SCLS owns 75% Keller
owns 25%. Still a $9 million building. Keller
would lease their 25% back to SCLS. In 20 years SCLS buys 25% from Keller
Option B: Reduce the size of the Walton Commons building - Done
·
Each department do a needs assessment to evaluate what we can live
without and what is required in downsized building.
Option C: Purchase existing office building and add on
Delivery
·
D. Haug will continue to shop for
buildings
Option D: Purchase office building and continue to lease
Delivery
Option E: Keep leasing and walk away (if A-D don’t work)
Option F: Building efficiencies to create room in budget
Homework for Next Meeting:
Cross
easements agreements for parking? D. Haug will ask
Marty Rifkin for information
What
are the covenants in place attached to the parcel? Attorney is reviewing
Which
is the driveway for us to access Lakeland University? D. Haug will
research
Ground
lease details. Attorney is reviewing
Dane
County Airport building design rules.
Is
there a required number of parking spaces and how is the number calculated? D. Haug reviewing
Lakeland area
architectural review committee? “Design and Review Committee” – what are their
requirements? What sides constitute the façade?
K. Goeden will forward covenants and legal documents
to R. Lindstrom for review
R. Lindstrom will sketch
up both plans. Needs answers from
covenants and easements. Requested
feedback from BNAW on both plans. Floor Plan and site layout. Need to know how much land is needed.
D. Flanigan
will work on rough estimates for both options.
Engineers working on ball park figures.
D. Flanigan
will send sketches so work group can move puzzle pieces and provide feedback for
2 options for next meeting.
D. Haug
needs to find cost of additional land and which is viable west or north side Need 5,000 or 10,000 additional toward Pankratz or pan handle/dog leg.
K. Goeden will contact
lawyer for information on title work
D. Flanigan
will bring cost and terms of Keller leasing back 25% of the original ($9
million version) Walton Commons building to SCLS
Set up weekly check-ins on
Friday for D. Haug, D. Flanigan,
M. Van Pelt and K. Goeden on Blue Jeans
M. Van Pelt will put
recommendation to eliminate the revised Walton Commons plan (the $7.6 million -
$8.1 million plan) on the July SCLS
Board agenda
D. Haug
will update the critical controls calendar with prioritization of which items
need to be done first and who is responsible for completing
Next Meeting:
July
21, 2022 1:00 Wintergreen Resort in the Wisconsin Dells after the All Directors
Meeting
60
Gasser Rd, Wisconsin Dells, WI, in front of the Outlet Mall.
Adjournment: 12:15 pm
Topics tabled for upcoming meetings:
· Schedule Admin and Delivery meetings to discuss shared HR and
filing spaces
· Median Update
· CSM/CUP Updates
· Utility Applications
o Fiber,
power, water, phone, cable, internet, airport permit?
· Building Permit
Parking Lot:
·
Notify Michelle Drea at the