Building
Needs Assessment Work Group Minutes
August
18, 2022 1:00 – 3:00 pm
Present:
Jean
Anderson SCLS Consulting
Services Coordinator
Corey
Baumann SCLS Delivery Services
Coordinator
Kerrie
Goeden SCLS
HR & Finance Coordinator
Gary
Poulson SCLS Board Chair
Jesse
Stewart SCLS Fleet Manager
Vicki
Teal SCLS Technology
Services Coordinator
Kristi
Williams SCLS Board Trustee
Martha
Van Pelt SCLS Director
Guests:
Susan Feith SCLS Board Trustee
Devin Flanigan Keller Project Manager
Deb
Haeffner SCLS Consultant
Rob
Lindstrom Keller Architect
Absent:
Nan
Brien SCLS Board
Trustee
David Haug Lighthouse
Realty
Call to Order by K. Goeden at 1:03
Approval of previous meeting minutes: August 4, 2022
a.
Motion by J. Stewart to approve the minutes
b.
Second by J. Anderson
c. Approved
Reports:
· Walton
Commons closure – K. Goeden, M. Van Pelt
o Letter
to terminate offer done by Attorney Lawton along with request to return earnest
money $15,000. Will go to SCLS Board for
approval and signature at the August Board of Trustees meeting. Then M. Van Pelt will forward these documents
to the appropriate people at the City of Madison.
Discussion:
· Lakeland University
o
Review
updated sketch and site plan – R. Lindstrom
o
Shared
new drawing; 42 parking stalls, we are below building ratio to lot which is
good, lot coverage may be high (zoning or covenant says 75% max lot coverage) resulting in 25% of green space. R. Lindstrom
is working on it to determine the actual amount. R. Lindstrom says his opinion after reading
the land documents is there are cross easements for driveways and parking – so
42 stalls are okay as we would have access to other parking. Declaration of Reciprocal Easement document
addresses this. We can use other lots’ spaces. K. Goeden
will reach out to owner’s attorney for confirmation. We will also verify this
with the City of Madison at the upcoming DAT meeting.
o
New
Floor Plan:
§ Overall, the group is very happy with
the proposed design. It incorporates
most of what we had in the Walton Commons plan.
§ 30” side lights in dedicated offices
he added, to match existing structure.
§ Cubicles: same size 7x7 spaces each
which allows for collaborative space in the center of the room
§ Workroom is bigger than in previous
plans
§ Removed doors and replaced with two
large archways to work room
§ Did not touch restrooms, janitor
closet, kitchen or break area which is larger than any other plan
§ Use existing electrical closet and
telco closet
§ Maker area is entire classroom with
open shelving for storage
§ Data Center had to add a permanent
wall because the existing wall between the Data Center and the Tech Prep Room
is a folding wall. Placed the wall so as
to expand Tech Prep Room and make Data Center smaller.
§ Delivery plan; The Delivery addition
fits nicely on the lot. It is within the setback boundaries from Packer Ave. as
well. Remove 1 former vestibule door at
that end of the building. And replace with 1 double wide door to sorting floor.
Close off hallway door to classroom to create new delivery offices. Probably do bar joist construction. Existing
building is conventional steel frame, bar joist and veneer masonry.
§ Loading docks are 12’ 6” on center for
overhead doors location. Triangle shapes
on drawing are cushions for loading docks – energy requirement
§ Turning radius of new driveway will be
reviewed. Keller has software to run
scenarios of trucks using driveway.
§ Next steps
§ Submit to Dane County Airport for
review
§ Submit to DAT for review (R. Lindstrom’s
new drawings will be sent to DAT) with 1 sentence statement from D. Flanigan.
o
Attend
8/25/22 DAT meeting. DAT will be via Zoom
o
Budget
estimate timeline – D. Flanigan
§ Plans will now go to Keller estimators
§ Estimators will compile cost estimates
for BNAW to discuss at 9/1/22 BNAW meeting
· Critical controls calendar for
Lakeland – Contingency Updates
§ Ground lease review
§ SCLS and Dane County attorneys have
reviewed
§ D. Flanigan
is scheduling ALTA survey now to start on 9/1/2022 – waiting on budget estimate
before starting.
§ Estoppel letters in progress (states
when the lease ends)
o
Attorney
Lawton working on the Lakeland & Dane County letters.
§ Approval of lease assignment to SCLS –
follow up
o
Attorney
Lawton has the assignment and assumption consent documents from Dane County
(this will follow the approvals with Dane County on the building/construction
issues they are looking at).
o
D.
Haug confirming with the owner of lot 46 (right of
Lakeland when facing front door) to the north of Lot 3 that there are no
outstanding amounts owed/issue or disputes as to the driveway (north access for
our site) that Lot 3 and Lot 46 are responsible for (each 50-50).
§ Insurance provision – follow up
o
K.
Goeden contacting Hausmann
Insurance
§ Financing
§ K. Goeden
reached out to BCPL for options on how to handle 6 month extension of project
plan. BCPL offered an interest only loan
for year 1. Shared with SCLS Board
Personnel and Budget & Finance Committees on 8/17. This option will save SCLS
$140,000 on the first mortgage payment in year 1 (2023).
§ We have to make a mortgage payment in
2023 no matter what, so restructuring to an interest only payment in year 1
will afford SCLS the greatest flexibility financially with the 2023 budget, to
allow for all scenarios to fit within the budget.
§ 2nd loan with BCPL. K. Goeden requested
application. Delayed the request so first payment does not hit until 2024. SCLS
Board approved a 2nd loan of $1 million on 1/27/2022 to create the
total budget of $7 million.
§ Reiterated budget of $7 million
maximum for entire project. If the Keller estimators come back with a cost
estimate for the proposed design that is within budget, we will continue to
move forward.
§ Building inspection
§ D. Flanigan
doing walk through with contractors 8/19 at 10:00. He arranged 2 owners of different contractor companies
to perform the inspection.
§ Proposed use
§ Preliminary OK from Airport and City
of Madison
§ Submitting site plans for review to
Airport group and City of Madison Design Assistance Team (DAT).
§ ALTA Survey/Zoning/Easement/Expansion
§ ALTA survey will commence on 9/1/22 if
the proposed design is in budget.
§ Title Insurance and Title Documents
§ Take ALTA survey and give to the title
company for endorsements to title insurance and title insurance commitment
markup (including removing exceptions determined not to apply to the property
based on what the survey shows).
§ City of Madison Review and Approval
§ DAT meeting on 8/25/22
§ Submit site plan to DAT by 8/19/22
noon, D. Flanigan doing it.
§ Dane County Airport Review and
Approval
§ Submit site plan and elevations for
review. R. Lindstrom will prepare elevations
by 9/1 meeting. Keller building design exterior
will mimic current building to meet requirements.
§ Phase 1 ESA
§ D. Flanigan scheduling to begin 9/1 if
the proposed design is within budget.
Needs 2 weeks from notice to completion.
· Review our timeline
o
Assign
any remaining contingency work
§ Reach out to City of Madison alderman to provide
30 day notice of applying for a conditional use permit.
§ Solar discussion. Group said do not pursue since it is not in
our budget and we did not get awarded the grants.
§ No installation of electrical
infrastructural to support EV fleet vehicles.
Not in budget.
Topics tabled for Upcoming meetings:
· Review Other Options to Consider
Purchase
office building and continue to lease Delivery
Keep
leasing and walk away (if no other options work)
·
Schedule Admin and
Delivery meetings to discuss shared HR and filing spaces
·
Building
Permit
Homework for Next Meeting:
K.
Goeden will submit site map and floor plan to Adam
Ussher, Airport Attorney
D.
Flanigan will send site plan and 1 sentence
description to City of Madison Design Assistance Team (DAT)
D.
Flanigan ALTA survey being scheduled to discover any
encumbrances on parcel
K.
Goeden follow up with attorneys on Estoppel letters
K.
Goeden will reach out to owner’s attorney for
confirmation of Declaration of Reciprocal Easement meaning that we have use of
all parking spaces.
K.
Goeden will follow up on insurance provision as
referenced by attorney on the ground lease.
D.
Haug confirming with the owner of lot 46 (right of
Lakeland when facing front door) to the north of Lot 3 that there are no
outstanding amounts owed/issue or disputes as to the driveway (north access for
our site) that Lot 3 and Lot 46 are responsible for (each 50-50).
D.
Flanigan will schedule Phase 1 ESA to begin 9/1. Needs 2 weeks from notice to completion.
Future
item: Reach out to City of Madison Alderman for 30 days’ notice of Conditional
Use Plan
Next Meeting:
September
1, 2022 10:00 am – 12:00 pm
Adjournment: 2:31
Parking Lot:
· Notify
Michelle Drea at the City of Madison Assessor’s
office when we purchase a site.
mdrea@cityofmadison.com